Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.645 | 2.645 | 2.140 | 0.505 | 0.500 | 0.000 |
71W839 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter 44547 Dated 27/02/2023
TS Amount (lakhs) : 118.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
118.41
Resanction Cost :
118.41
Tentative Cost :
118.41
Exp. Upto Last Fy : 95.94
For CFY 2024-2025
Remaining : 22.47
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 95.94
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
27 Feb 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024
Physical Peramenters