Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.79 | 1.79 | 1.000 | 0.79 | 0.790 | 0.000 |
71W840 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter 44547 Dated 27/02/2023
TS Amount (lakhs) : 121.59 Lacs
Financial Detail
Sanction Cost : 121.59 Lacs
Resanction Cost : 121.59 Lacs
Exp. Upto Last Fy : 46.68 Lacs
For CFY 2024-2025
Remaining : 74.91 Lacs
Demand : 70.00 Lacs
Allotment : 40.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 46.68 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 2 months ago
27 Feb 2023
Tentative Completion date:
1 month 5 days from now
25 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 कि0मी0 में इण्टर लाॅकिंग टाईल्स का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 19-Feb-2024
Physical Peramenters