Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
71W851 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 111279 दिनांक 29/3/2023
TS Amount (lakhs) : 4.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 4.40
Demand : 1.04
Allotment : 1.04
Exp in CFY : 1.04
Total Up to Date Exp : 1.14
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 2 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य प्रगति पर। -- as on 11-Apr-2023
Physical Peramenters