Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
71W865 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 38666/111504 दिनांक 31/3/2023
TS Amount (lakhs) : 181.54 Lacs
Financial Detail
Sanction Cost : 181.54 Lacs
Resanction Cost : 181.54 Lacs
Exp. Upto Last Fy : 141.16 Lacs
For CFY 2024-2025
Remaining : 40.38 Lacs
Demand : 40.00 Lacs
Allotment : 20.61 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 141.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
3 months 3 weeks from now
15 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2 कि0मी0 में इण्टर व टाॅप कार्य पूर्ण। शेष कार्य प्रगति पर।
(3 वर्षो के अनुरक्षण का प्राविधान स्वीकृत आगणन में हैं। शेष 2 वर्षो के अनुरक्षण के प्राविधान हेतु रू0 8.95 लाख की अतिरिक्त मांग की गई है।)
-- as on 19-Feb-2024
Physical Peramenters