Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21.281 | 21.281 | 0.000 | 21.281 | 21.300 | 2.500 |
71W871 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लोक निर्माण विभाग देहरादून के पत्रांक-895/07 याता- पी0एम0 जी0एस0वाई0-नि0 ।।। दिनांक 16/5/2023
TS Amount (lakhs) : 416.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
416.02
Resanction Cost :
416.02
Tentative Cost :
416.02
Exp. Upto Last Fy : 138.27
For CFY 2024-2025
Remaining : 277.75
Demand : 277.75
Allotment : 8.00
Exp in CFY : 0.82
Total Up to Date Exp : 139.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 85 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
17.50 कि0मी0 पी0सी0 कार्य पूर्ण। नाली,स्कपर, दीवार, काॅजवे का कार्य प्रगति पर। -- as on 25-Jun-2024
Physical Peramenters