Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17.175 | 17.175 | 0.000 | 17.175 | 17.200 | 10.000 |
71W872 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख अभियन्ता एवं विभागाध्यक्ष, लोक निर्माण विभाग देहरादून के पत्रांक-895/07 याता- पी0एम0 जी0एस0वाई0-नि0 ।।। दिनांक 16/5/2023
TS Amount (lakhs) : 420.75 Lacs
Financial Detail
Sanction Cost : 420.75 Lacs
Resanction Cost : 420.75 Lacs
Exp. Upto Last Fy : 243.66 Lacs
For CFY 2024-2025
Remaining : 177.09 Lacs
Demand : 177.09 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 243.66 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 70 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
10 कि0मी0 में पी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-May-2024
Physical Peramenters