Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17.175 | 17.175 | 0.000 | 17.175 | 17.200 | 10.000 |
71W872 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख अभियन्ता एवं विभागाध्यक्ष, लोक निर्माण विभाग देहरादून के पत्रांक-895/07 याता- पी0एम0 जी0एस0वाई0-नि0 ।।। दिनांक 16/5/2023
TS Amount (lakhs) : 420.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
420.75
Resanction Cost :
420.75
Tentative Cost :
420.75
Exp. Upto Last Fy : 243.66
For CFY 2024-2025
Remaining : 177.09
Demand : 177.09
Allotment : 105.00
Exp in CFY : 103.89
Total Up to Date Exp : 347.55
Work completed
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 weeks 6 days ago
20 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 15-Jun-2024
Physical Peramenters