Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24 | 24 | 0.000 | 24 | 24.000 | 7.000 |
71W873 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लोक निर्माण विभाग देहरादून के पत्रांक-895/07 याता- पी0एम0 जी0एस0वाई0-नि0 ।।। दिनांक 16/5/2023
TS Amount (lakhs) : 329.08 Lacs
Financial Detail
Sanction Cost : 329.08 Lacs
Resanction Cost : 329.08 Lacs
Exp. Upto Last Fy : 57.67 Lacs
For CFY 2024-2025
Remaining : 271.41 Lacs
Demand : 271.41 Lacs
Allotment : 101.13 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 57.67 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 30 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
7.00 कि0मी0 में पी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-May-2024
Physical Peramenters