Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.543 | 1.543 | 0.000 | 1.543 | 1.540 | 1.540 |
71W874 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 44547 दिनांक 03/05/2023
TS Amount (lakhs) : 80.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
80.34
Resanction Cost :
80.34
Tentative Cost :
80.34
Exp. Upto Last Fy : 1.46
For CFY 2024-2025
Remaining : 78.88
Demand : 70.00
Allotment : 26.12
Exp in CFY : 26.12
Total Up to Date Exp : 27.58
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
03 May 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-May-2024
Physical Peramenters