Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
71W876 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0-2825/उ0म0प्र0 (वा0)/सिडकूल/2023 दि0 8/2/2023
TS Amount (lakhs) : 47.27 Lacs
Financial Detail
Sanction Cost : 47.27 Lacs
Resanction Cost : 47.27 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 47.27 Lacs
Demand : 47.27 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 3 months ago
08 Feb 2023
Tentative Completion date:
3 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 28-Jun-2023
Physical Peramenters