Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.22 | 4.22 | 0.600 | 3.62 | 3.000 | 0.500 |
71W927 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 240.89 Lacs
Financial Detail
Sanction Cost : 240.89 Lacs
Resanction Cost : 240.89 Lacs
Exp. Upto Last Fy : 46.21 Lacs
For CFY 2024-2025
Remaining : 194.68 Lacs
Demand : 150.00 Lacs
Allotment : 54.88 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 46.21 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 30 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
10 months 19 hours from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.100 कि0मी0 में इण्टर लाॅकिंग टाईल्स का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-May-2024
Physical Peramenters