Work Profile Report [71W927]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 240.89 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
240.89
Resanction Cost :
240.89
Tentative Cost :
240.89
Exp. Upto Last Fy :
236.24
For CFY 2025-2026
Remaining :
4.65
Demand :
0.00
Allotment :
4.65
Exp in CFY :
0.00
Total Up to Date Exp :
236.24
Work completed
Sanction on : 2 years 2 months ago
21 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
30 Dec 2024
Actual Completion Date : 8 months 3 weeks ago
30 Dec 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: