Work Profile Report [71W928]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 107.1 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
107.10
Resanction Cost :
107.10
Tentative Cost :
107.10
Exp. Upto Last Fy :
106.53
For CFY 2025-2026
Remaining :
0.57
Demand :
0.00
Allotment :
16.91
Exp in CFY :
0.00
Total Up to Date Exp :
106.53
Work completed
Sanction on : 1 year 10 months ago
21 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
100 %
Tentative Completion date on : 11 months 3 weeks ago
13 Jun 2024
Actual Completion Date : 4 months 2 weeks ago
19 Jan 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025
Assets :
Work not linked with IM