Length of Road [Km] | 2.54 | 2.54 | 0.000 | 2.54 | 2.540 | 0.000 |
71W928 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 107.1 Lacs
Financial Detail
Sanction Cost : 107.10 Lacs
Resanction Cost : 107.10 Lacs
Exp. Upto Last Fy : 89.62 Lacs
For CFY 2024-2025
Remaining : 17.48 Lacs
Demand : 17.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 89.62 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-Jan-2024