Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.54 | 2.54 | 0.000 | 2.54 | 2.540 | 0.000 |
71W928 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 107.1 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
107.10
Resanction Cost :
107.10
Tentative Cost :
107.10
Exp. Upto Last Fy : 89.62
For CFY 2024-2025
Remaining : 17.48
Demand : 15.96
Allotment : 11.11
Exp in CFY : 10.89
Total Up to Date Exp : 100.51
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 4 days ago
13 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 29-Jun-2024
Physical Peramenters