Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 0.000 | 1.8 | 1.800 | 0.000 |
71W930 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 150.49 Lacs
Financial Detail
Sanction Cost : 150.49 Lacs
Resanction Cost : 150.49 Lacs
Exp. Upto Last Fy : 28.55 Lacs
For CFY 2024-2025
Remaining : 121.94 Lacs
Demand : 100.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 28.55 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 3 weeks ago
25 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्लम द्वारा सुरक्षात्मक कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 27-Feb-2024
Physical Peramenters