Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.265 | 1.265 | 0.000 | 1.265 | 1.260 | 0.900 |
71W931 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 139.85 Lacs
Financial Detail
Sanction Cost : 139.85 Lacs
Resanction Cost : 139.85 Lacs
Exp. Upto Last Fy : 56.45 Lacs
For CFY 2024-2025
Remaining : 83.40 Lacs
Demand : 60.00 Lacs
Allotment : 11.53 Lacs
Exp in CFY : 11.53 Lacs
Total Up to Date Exp : 67.98 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 70 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
7 months 5 days from now
25 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 03-Feb-2024
Physical Peramenters