Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.265 | 1.265 | 0.000 | 1.265 | 1.260 | 0.900 |
71W931 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-40068/45994 दिनांक 21/07/2023
TS Amount (lakhs) : 139.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
139.85
Resanction Cost :
139.85
Tentative Cost :
139.85
Exp. Upto Last Fy : 56.45
For CFY 2024-2025
Remaining : 83.40
Demand : 60.00
Allotment : 74.07
Exp in CFY : 74.07
Total Up to Date Exp : 130.52
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
5 months 1 week from now
25 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 27-Jun-2024
Physical Peramenters