Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.99 | 5.99 | 5.990 | 0 | 0.000 | 0.000 |
71W934 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-45635/48456़ दिनांक 10/08/2023
TS Amount (lakhs) : 70.27 Lacs
Financial Detail
Sanction Cost : 70.27 Lacs
Resanction Cost : 70.27 Lacs
Exp. Upto Last Fy : 61.40 Lacs
For CFY 2024-2025
Remaining : 8.87 Lacs
Demand : 8.87 Lacs
Allotment : 8.87 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 61.40 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण। कच्ची नाली/स्कपर का कार्य प्रगति पर। -- as on 06-Apr-2024