Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12 | 0 |
71W936 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2937/।।। (2)/23-01 (प्रा0आ0)/2019 दिनांक 11/8/2023
TS Amount (lakhs) : 49.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
49.91
Resanction Cost :
49.91
Tentative Cost :
49.91
Exp. Upto Last Fy : 16.52
For CFY 2024-2025
Remaining : 33.39
Demand : 33.39
Allotment : 30.00
Exp in CFY : 0.00
Total Up to Date Exp : 16.52
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
11 months 6 days ago
11 Aug 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 27-Jun-2024
Physical Peramenters