Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12 | 0 |
71W936 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2937/।।। (2)/23-01 (प्रा0आ0)/2019 दिनांक 11/8/2023
TS Amount (lakhs) : 49.91 Lacs
Financial Detail
Sanction Cost : 49.91 Lacs
Resanction Cost : 49.91 Lacs
Exp. Upto Last Fy : 16.52 Lacs
For CFY 2024-2025
Remaining : 33.39 Lacs
Demand : 33.39 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 16.52 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 40 %
Sanction on :
9 months 1 week ago
11 Aug 2023
Tentative Completion date:
2 months 1 week from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
10 कि0मी0 में क्रैश बेरियर का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-May-2024
Physical Peramenters