Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
71W949 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-148143/44547़ दिनांक 21/08/2023
TS Amount (lakhs) : 257.17 Lacs
Financial Detail
Sanction Cost : 257.17 Lacs
Resanction Cost : 257.17 Lacs
Exp. Upto Last Fy : 176.67 Lacs
For CFY 2024-2025
Remaining : 80.50 Lacs
Demand : 80.50 Lacs
Allotment : 75.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 176.67 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
8 months 4 weeks ago
21 Aug 2023
Tentative Completion date:
1 month 1 week from now
28 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कर्टेनवाल एवं स्ट्रीम बैड का निर्माण कार्य प्रगति पर। -- as on 07-Mar-2024
Physical Peramenters