Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
71W949 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रावली सं0-148143/44547़ दिनांक 21/08/2023
TS Amount (lakhs) : 257.17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
257.17
Resanction Cost :
257.17
Tentative Cost :
257.17
Exp. Upto Last Fy : 176.67
For CFY 2024-2025
Remaining : 80.50
Demand : 80.50
Allotment : 75.00
Exp in CFY : 64.66
Total Up to Date Exp : 241.33
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 90 %
Sanction on :
10 months 3 weeks ago
21 Aug 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कर्टेनवाल एवं स्ट्रीम बैड का निर्माण कार्य प्रगति पर। -- as on 07-Mar-2024
Physical Peramenters