Work Profile Report [71W957]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्रावली संख्या 33334 दिनांक 26/09/2023
TS Amount (lakhs) : 95.47 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
95.47
Resanction Cost :
95.47
Tentative Cost :
95.47
Exp. Upto Last Fy :
7.56
For CFY 2024-2025
Remaining :
87.91
Demand :
25.00
Allotment :
15.42
Exp in CFY :
15.42
Total Up to Date Exp :
22.98
Construction Started
Sanction on : 1 year 2 months ago
26 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
50 %
Tentative Completion date on : 2 months 3 weeks from now
20 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 05-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand