Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 2.000 | 0.800 |
71W957 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 33334 दिनांक 26/09/2023
TS Amount (lakhs) : 95.47 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
95.47
Resanction Cost :
95.47
Tentative Cost :
95.47
Exp. Upto Last Fy : 7.56
For CFY 2024-2025
Remaining : 87.91
Demand : 50.00
Allotment : 4.53
Exp in CFY : 4.53
Total Up to Date Exp : 12.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 20 %
Sanction on :
9 months 3 weeks ago
26 Sep 2023
Tentative Completion date:
8 months 2 days from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Apr-2024
Physical Peramenters