Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 2.000 | 0.800 |
71W957 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 33334 दिनांक 26/09/2023
TS Amount (lakhs) : 95.47 Lacs
Financial Detail
Sanction Cost : 95.47 Lacs
Resanction Cost : 95.47 Lacs
Exp. Upto Last Fy : 7.56 Lacs
For CFY 2024-2025
Remaining : 87.91 Lacs
Demand : 50.00 Lacs
Allotment : 3.65 Lacs
Exp in CFY : 3.65 Lacs
Total Up to Date Exp : 11.21 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 20 %
Sanction on :
7 months 3 weeks ago
26 Sep 2023
Tentative Completion date:
10 months 19 hours from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Apr-2024
Physical Peramenters