Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 4 | 4 | 0 | 4 | 4 | 0 |
Span of Bridges [m] | 47 | 47 | 0.000 | 47 | 47.000 | 0.000 |
71W965 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 45994 दिनांक 12/12/2023
TS Amount (lakhs) : 369.6 Lacs
Financial Detail
Sanction Cost : 369.60 Lacs
Resanction Cost : 369.60 Lacs
Exp. Upto Last Fy : 31.72 Lacs
For CFY 2024-2025
Remaining : 337.88 Lacs
Demand : 332.50 Lacs
Allotment : 150.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 31.72 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
5 months 1 week ago
12 Dec 2023
Tentative Completion date:
9 months 1 week from now
28 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 07-Mar-2024
Physical Peramenters