Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 47 | 47 | 47 | 0 |
71W985 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 272/।।। (2)/2024-01(प्रा0आ0)/2023 दिनांक 31/1/2024
TS Amount (lakhs) : 337.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
337.35
Resanction Cost :
337.35
Tentative Cost :
337.35
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 337.35
Demand : 337.35
Allotment : 116.89
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
1 month 1 week from now
29 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Apr-2024
Physical Peramenters