Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 72 | 72 | 72 | 0 |
71W986 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-272/।।। (2)/2024-01(प्रा0आ0)/2023 दिनांक 31/1/2024
TS Amount (lakhs) : 266.74 Lacs
Financial Detail
Sanction Cost : 266.74 Lacs
Resanction Cost : 266.74 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 266.74 Lacs
Demand : 266.74 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
4 months 22 hours from now
20 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
34 कि0मी0 में क्रैश बेरियर का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-May-2024