Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 1.200 | 0 | 0.000 | 0.000 |
71W992 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, उत्तराखण्ड, देहरादून के पत्रांक-276/14 प्रा0याता (क)-उ0/2023 दि0 22/02/2024
TS Amount (lakhs) : 21.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.39
Resanction Cost :
21.39
Tentative Cost :
21.39
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 21.39
Demand : 21.39
Allotment : 21.39
Exp in CFY : 10.62
Total Up to Date Exp : 10.62
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 months 3 weeks ago
22 Feb 2024
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण।दायित्व शेष। -- as on 06-Apr-2024
Physical Peramenters