Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 325 | 325 | 0.000 | 325 | 0.000 | 0.000 |
71W997 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 44547 दिनांक 24/02/2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2675.95
Resanction Cost :
2675.95
Tentative Cost :
2675.95
Exp. Upto Last Fy : 0.05
For CFY 2024-2025
Remaining : 2,675.90
Demand : 1,338.37
Allotment : 312.00
Exp in CFY : 121.11
Total Up to Date Exp : 121.16
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
4 months 3 weeks ago
24 Feb 2024
Tentative Completion date:
1 year 8 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Apr-2024
Physical Peramenters