Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 6.02 | 6.02 | 0 |
72W125 :
Work not linked with IM
Bridges on The Basis of AI: Near Maithanaghat Pedestrain bridge
Administrative Approval Detail : शा0सं0 1542 /111(2)/09-23(मु0मं0घो0)/09 दि0 31.03.2010
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
350.00
Resanction Cost :
350.00
Tentative Cost :
350.00
Exp. Upto Last Fy : 238.16
For CFY 2024-2025
Remaining : 111.84
Demand : 55.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 238.16
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
14 years 3 months ago
31 Mar 2010
Tentative Completion date:
1 year 8 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
वनभूमि प्रस्ताव एफ0पी0यू0के0/रोड /43504/2019 दि0 27.12.2019, अपर सचिव उत्तराखण्ड शासन देहरादून के पत्रांक 171/एक्स-3- 20/1(16)2020 दि0 18.3.20 के द्वारा सैद्धान्तिक स्वीकृति प्राप्त। स्वीकृत लागत के अन्तर्गत तकनीकी स्वीकृति कुल 4.00 किमी0 हेतु प्राप्त है। जिसमें की 4.00 किमी0 में पहाड कटान एवं पार्ट-2 का कार्य पूर्ण कर लिया गया है। शेष 2.00 किमी0 में ग्रामवासियों द्वारा विवाद किया जा रहा है। जिस कारण कार्य बाधित है। विवाद सुलाझाये जाने हेतु दि0 13.03.2024 को ग्रामवासियों के साथ बैठक की गयी। सहमति नही बन पाई। -- as on 03-Apr-2024
Physical Peramenters