Work Profile Report [72W125]

fवधानसभा बीरोंखाल के अन्तर्गत एन0एच0बैण्ड से कोfठला fखटोfटया मोटर मार्ग का fनर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0सं0 1542 /111(2)/09-23(मु0मं0घो0)/09 दि0 31.03.2010

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

350.00

Resanction Cost :

350.00

Tentative Cost :

350.00

Exp. Upto Last Fy :

238.16

For CFY 2024-2025

Remaining :

111.84

Demand :

55.00

Allotment :

0.00

Exp in CFY :

2.00

Total Up to Date Exp :

240.16

Construction Started

Sanction on : 14 years 7 months ago

31 Mar 2010

Physical Progress:

At start of FY 2024-2025 :

65 %

Up to Date :

65 %

Tentative Completion date on : 1 year 4 months from now

30 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
6.02
4.000
2.02
0.000
0.000

Remark

view all

इस कार्यालय के पत्रांक 1908/14सी0 दि0 23.10.2024 द्वारा CA Muatation Details के बारे में चाही गई सूचना परिवेश 1.0 पोर्टल में अपडेट की गयी व विधिवत स्वीकृति निर्गत किये जाने हेतु नोडल अधिकारी देहरादून को अनुरोध पत्र प्रेषित किया गया व सम्बन्धित सहायक अभियन्ता को व्यक्ति रूप से नोडल कार्यालय में उपस्थित होकर प्रकरण में अद्यतन कार्यवाही करने हेतु निर्देशित किया गया। वर्तमान में प्रकरण नोडल स्तर पर परीक्षण में है। -- as on 05-Nov-2024

Rating : 83

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: Near Maithanaghat Pedestrain bridge