Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
72W151 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6836/111(2)/11-03(मुुं0मं0घो0)/2011 दि0 25.03.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 126.00 Lacs
Resanction Cost : 126.00 Lacs
Exp. Upto Last Fy : 120.30 Lacs
For CFY 2024-2025
Remaining : 5.70 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 120.30 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
13 years 1 month ago
25 Mar 2011
Tentative Completion date:
10 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
विधिवत स्वीकृति प्राप्त किये जाने हेतु स्टेज-2 में अनुपालन आख्या जाॅन र्लान दि0 05.04.2018 को अपलोड की गई है। वर्तमान में प्रकरण भारत सरकार स्तर पर लम्बित। पत्रांक 65/14 सी0 दि0 13.01.2020 द्वारा भारत सरकार उत्तर मध्य क्षेत्र को प्रथम अनुस्मारक पत्र लिखा ेगया है। पत्रांक 511/14सी0 दि0 30.03.2021 द्वारा तृतीय एवं पत्रांक 869/14 सी0 दि0 05.07.2021 द्वारा चतुर्थ अनुस्मारक पत्र लिखा गया है। द्वितीय चरण की स्वीकृति प्राप्त एवं द्वितीय चरण का कार्य पूर्ण। -- as on 05-Nov-2023
Physical Peramenters