Work Profile Report [72W152]

fवकासखण्ड थलीसैंण के अन्तर्गत सेरामाण्डे सम्पर्क मार्ग पर लौह सेतु का fनर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 3836/111(2)/11-03 (मु0मं0घो0)/2011 दि0 25.03.2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Bridges State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

3.24

Resanction Cost :

3.24

Tentative Cost :

3.24

Exp. Upto Last Fy :

3.24

For CFY 2025-2026

Remaining :

0.00

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.24

Unstarted Work

Sanction on : 14 years 2 months ago

25 Mar 2011

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

10 %

Tentative Completion date on : 2 months 4 days ago

30 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (20m)
1 (20m)
1 (20m)
-

Remark

view all

जिस स्थान पर उक्त पैदल सेतु का निर्माण किया जाना था। वहा पर पी0एम0जी0एस0वाई0 द्वारा मोटर पुल का निर्माण कार्य किया जा रहा है। जिस कारण उक्त पैदल सेतु के निर्माण की आवश्यकता नही है। तथा उक्त कार्य को निरस्त किया जाना है। -- as on 07-Jul-2021

Rating : 100

No Forest Case in The Work

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand