Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 0.85 | 0.85 | 0 |
72W158 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4996)/।।।(2)/।।-84(प्रा0आ0)/2011 दि0 23.11.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.60
Resanction Cost :
12.60
Tentative Cost :
12.60
Exp. Upto Last Fy : 4.60
For CFY 2024-2025
Remaining : 8.00
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.60
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
12 years 7 months ago
23 Nov 2011
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण स्टेज-। की स्वीकृति प्राप्त। पहाड कटान का कार्य पूर्ण। -- as on 05-Feb-2024
Physical Peramenters