Work Profile Report [72W158]

fवधानसभा क्षेत्र बीरोंखाल के अन्तर्गत राजकीय इण्टर कालेज ग्वीनखाल तक मोटर मार्ग का fनर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 4996)/।।।(2)/।।-84(प्रा0आ0)/2011 दि0 23.11.2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

12.60

Resanction Cost :

12.60

Tentative Cost :

12.60

Exp. Upto Last Fy :

4.60

For CFY 2024-2025

Remaining :

8.00

Demand :

4.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

4.60

Construction Started

Sanction on : 13 years 1 month ago

23 Nov 2011

Physical Progress:

At start of FY 2024-2025 :

85 %

Up to Date :

85 %

Tentative Completion date on : 3 months 5 days from now

30 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
1
0.85
0.85
-

Remark

view all

द्वितीय चरण स्टेज-। की स्वीकृति प्राप्त। पहाड कटान का कार्य पूर्ण। -- as on 05-Feb-2024

Rating : 89

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: