Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 7.12 | 7.12 | 0 |
72W206 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5377/(1)/111(2)/12-13 (मु0मं0घो0)/2012 दि0 14-1-2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
126.00
Resanction Cost :
126.00
Tentative Cost :
126.00
Exp. Upto Last Fy : 44.64
For CFY 2024-2025
Remaining : 81.36
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 44.64
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
11 years 6 months ago
14 Jan 2013
Tentative Completion date:
1 year 8 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
FP/UK/ROAD485954/2024 दि0 05.07.2024 के द्वारा वनभूमि प्रस्ताव आॅनलाइन अपलोड कर दिया गया है। -- as on 05-Jul-2024
Physical Peramenters