Work Profile Report [72W300]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : वतकमत दव 362ध्ग्ग्प्ट.3ध्15ध्02;68द्ध2014 क्ज्ण्09 ड।त्ब्भ् 2015
TS Amount (lakhs) : 36.46 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
36.77
Resanction Cost :
44.26
Tentative Cost :
44.26
Exp. Upto Last Fy :
31.97
For CFY 2025-2026
Remaining :
12.29
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
31.97
Work completed
Sanction on : 10 years 2 months ago
09 Mar 2015
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 months ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। भवन को हस्तान्तरित किया जाना है। -- as on 10-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: