Work Profile Report [72W331]

Closed Work माननीय मुख्यमंत्री जी की घोषणा 54/2011 के अन्तर्गत मैखुली देवराड़ी कफलेख कठूरखाल मोटर मार्ग का निमा्रण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Nabard
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2693/।।।(2)/2017-38(एम0एल0ए0)/2017 दि0 28.09.2017

TS Amount (lakhs) : 470.9 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

470.92

Resanction Cost :

470.92

Tentative Cost :

470.92

Exp. Upto Last Fy :

470.87

For CFY 2024-2025

Remaining :

0.05

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

470.87

Work completed

Sanction on : 7 years 2 months ago

28 Sep 2017

Physical Progress:

At start of FY 2024-2025 :

90 %

Up to Date :

100 %

Tentative Completion date on : 3 years 5 months ago

30 Jun 2021

Actual Completion Date : 3 years 9 months ago

01 Mar 2021

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
10
10
-

Remark

view all

कार्य पूर्ण। -- as on 23-Mar-2023

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Sundergav Bridge