Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
72W334 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6096/।।।(2)/18-39 (एम0एल0ए0)/2017 दि0 17.12.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
19.75
Resanction Cost :
19.75
Tentative Cost :
19.75
Exp. Upto Last Fy : 15.20
For CFY 2024-2025
Remaining : 4.55
Demand : 4.55
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 15.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
5 years 7 months ago
17 Dec 2018
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण पर अनुमोदन प्राप्त। मुआवजा शेष। उक्त कार्य की द्वितीय चरण स्टेज-1 की स्वीकृति प्राप्त। कार्य प्रगति पर। -- as on 09-May-2023