Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
72W335 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 607/।।।(2)/19-38(एम0एल0ए0)/2017 दि0 07.02.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.40
Resanction Cost :
21.40
Tentative Cost :
21.40
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 21.40
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
5 years 5 months ago
07 Feb 2019
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। मुआवजा शेष। द्वितीय चरण स्टेज-। की स्वीकृति प्राप्त। -- as on 09-May-2023
Physical Peramenters