Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
72W336 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 607/।।।(2)/19-38(एम0एल0ए0)/2017 दि0 07.02.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 22.71 Lacs
Resanction Cost : 22.71 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 22.71 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
5 years 3 months ago
07 Feb 2019
Tentative Completion date:
10 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण पर अनुमोदन प्राप्त। मुआवजा शेष। द्वितीय चरण स्टेज-1 की स्वीकृति प्राप्त। -- as on 14-Jun-2021
Physical Peramenters