Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
72W342 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शां0 सं0 262/।।।(2)/20-38(एम0एल0ए0)/2017
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 49.40 Lacs
Resanction Cost : 49.40 Lacs
Exp. Upto Last Fy : 3.21 Lacs
For CFY 2024-2025
Remaining : 46.19 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3.21 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
4 years 4 months ago
13 Jan 2020
Tentative Completion date:
1 year 10 months from now
30 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
जिलाधिकारी पौडी के पत्रांक 1688/आठ-एल0ए0सी0-भू0ह0आ0/2021 पौड़ी दि0 09.11.2021 द्वारा दोगुनी क्षतिपूरक वृक्षारोपण भूमि उपलब्ध कराते हुये प्रभागीय वनाधिकारी पौडी के नाम हस्तान्तरण की स्वीकृति प्रदान की गयी है। डिजिटल मैप/के0एम0एल0 दि0 30.07.2022 को प्राप्त। वनभूमि प्रस्ताव गठित कर प्रतिहस्ताक्षर किये जाने के उपरान्त वनभूमि प्रस्ताव संख्या एफ0पी0/ यूके0/ रोड/ 413330/2023 दि0 06.01.2023 को आॅनलाईन अपलोड कर दी गई है। आॅनलाईन स्टेट्स अनुसार प्रभागीय वनाधिकारी स्तर पर लंबित। -- as on 30-Dec-2023
Physical Peramenters