Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.1 | 1.1 | 1.1 | 0 |
Closed Work 72W368 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Gas Godown Sundergav Bridge
Administrative Approval Detail : शा0 सं0-1286/।।।(2)/20-38(एम.एल.ए.)/2017टी0सी0 दिनांक 13.07.2020
TS Amount (lakhs) : 72.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
72.61
Resanction Cost :
72.61
Tentative Cost :
72.61
Exp. Upto Last Fy : 71.31
For CFY 2024-2025
Remaining : 1.30
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 71.31
Work completed
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 100 %
Sanction on :
4 years 4 days ago
13 Jul 2020
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 29-Dec-2022
Physical Peramenters