Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
72W383 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1354/।।।(2)/21-38 (एम0एल0ए0)2017 दि0 20.05.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.00
Resanction Cost :
60.00
Tentative Cost :
60.00
Exp. Upto Last Fy : 2.45
For CFY 2024-2025
Remaining : 57.55
Demand : 5.00
Allotment : 0.00
Exp in CFY : 1.07
Total Up to Date Exp : 3.52
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
3 years 1 month ago
20 May 2021
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त कार्य का समरेखण, अधीक्षण अभियन्ता 12 वाँ वृत्त, लो0नि0वि0 पौडी के पत्रांक 5105/1444 याताा- 12/2021 दि0 14.09.2021 द्वारा अनुमोदित। द्वितीय चरण स्टेज-। की स्वीकृति प्राप्त। अनुबन्ध गठित। पहाड कटान का कार्य पूर्ण। -- as on 05-Feb-2024
Physical Peramenters