Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 60 | 60 | 60 | 0 |
72W445 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 25463 लोे0नि0वि0 अनुभाग-2 देहरादून दि0 03.08.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
8.40
Resanction Cost :
8.40
Tentative Cost :
8.40
Exp. Upto Last Fy : 0.11
For CFY 2024-2025
Remaining : 8.29
Demand : 8.29
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.11
none
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 11 months ago
03 Aug 2022
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्थल चयन की कार्यवाही गतिमान है। -- as on 05-Feb-2024
Physical Peramenters