Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.8 | 0 |
72W450 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी का पत्रांक 768/वा0जि0यो0/सा0पत्रा0/2022-23 दिनांक 27.09.2022
TS Amount (lakhs) : 10 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy : 8.87
For CFY 2024-2025
Remaining : 1.13
Demand : 1.13
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 8.87
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 9 months ago
27 Sep 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 09-May-2023
Physical Peramenters