Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 4.65 | 4.65 | 0 |
72W457 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या 27910 लो0नि0वि0 अनुभाग-2 देहरादून दि0 14.12.2022
TS Amount (lakhs) : 137.05 Lacs
Financial Detail
Sanction Cost : 137.05 Lacs
Resanction Cost : 137.05 Lacs
Exp. Upto Last Fy : 118.16 Lacs
For CFY 2024-2025
Remaining : 18.89 Lacs
Demand : 18.89 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 118.16 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
1 year 5 months ago
14 Dec 2022
Tentative Completion date:
2 weeks 5 days ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.650 किमी0 तक पहाड कटान का कार्य पूर्ण। दायित्व शेष। -- as on 03-Mar-2024
Physical Peramenters