Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
72W467 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 कम्प्यूटरजनित क्रमांक- 1/111177/2023 ई-पत्रावली संख्या 36086 दि0 29-03-2023
TS Amount (lakhs) : 197.36 Lacs
Financial Detail
Sanction Cost : 197.36 Lacs
Resanction Cost : 197.36 Lacs
Exp. Upto Last Fy : 134.94 Lacs
For CFY 2024-2025
Remaining : 62.42 Lacs
Demand : 47.36 Lacs
Allotment : 24.78 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 134.94 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
1 year 1 month ago
29 Mar 2023
Tentative Completion date:
3 months 1 week from now
28 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित।स्कपर एवं दीवार निर्माण का कार्य पूर्ण। जी0-1, जी0-2 एवं जी0-3 का कार्य पूर्ण। पी0सी0 का कार्य पूर्ण। दायित्व शेष। अन्य अवशेष कार्य प्रगति पर। -- as on 15-Apr-2024
Physical Peramenters