Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.61 | 6.61 | 6.61 | 0 |
72W481 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमख अभियन्ता (विभागाध्यक्ष) लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0- नि0।।। दि0 16.05.2023
TS Amount (lakhs) : 127.56 Lacs
Financial Detail
Sanction Cost : 127.56 Lacs
Resanction Cost : 127.56 Lacs
Exp. Upto Last Fy : 78.05 Lacs
For CFY 2024-2025
Remaining : 49.51 Lacs
Demand : 49.51 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 78.05 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
2 months 3 weeks ago
28 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters