Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.61 | 6.61 | 6.61 | 0 |
72W481 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमख अभियन्ता (विभागाध्यक्ष) लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0- नि0।।। दि0 16.05.2023
TS Amount (lakhs) : 127.56 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
127.56
Resanction Cost :
127.56
Tentative Cost :
127.56
Exp. Upto Last Fy : 78.05
For CFY 2024-2025
Remaining : 49.51
Demand : 49.51
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 78.05
Work completed
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
4 months 2 weeks ago
28 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण।अनुबन्ध के अन्तिमिकरण की कार्यवाही की जा रही है। -- as on 28-Jun-2024
Physical Peramenters