Length of Road [Km] | 1.6 | 1.6 | 1.6 | 0 |
72W487 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-48456 दि0 14.07.2023
TS Amount (lakhs) : 30.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.35
Resanction Cost :
30.35
Tentative Cost :
30.35
Exp. Upto Last Fy : 27.97
For CFY 2024-2025
Remaining : 2.38
Demand : 2.38
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.97
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
14 Jul 2023
Tentative Completion date:
3 months 2 weeks ago
29 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 28-Jun-2024