Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.500 | 0 | 0.000 | 0.000 |
72W488 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-48456 दि0 14.07.2023
TS Amount (lakhs) : 73.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
73.60
Resanction Cost :
73.60
Tentative Cost :
73.60
Exp. Upto Last Fy : 52.77
For CFY 2024-2025
Remaining : 20.83
Demand : 20.83
Allotment : 0.00
Exp in CFY : 14.10
Total Up to Date Exp : 66.86
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 days ago
14 Jul 2023
Tentative Completion date:
3 months 2 weeks ago
29 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अनुबन्ध के अन्तिमिकरण की कार्यवाही की जा रही है। -- as on 28-Jun-2024
Physical Peramenters