Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.26 | 2.26 | 2.26 | 0 |
72W492 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0- ई.पत्रावली संख्या 48456 लो0नि0वि0 अनुभाग.2 देहरादून दि0 31.07.2023।
TS Amount (lakhs) : 45.11 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
45.11
Resanction Cost :
45.11
Tentative Cost :
45.11
Exp. Upto Last Fy : 28.43
For CFY 2024-2025
Remaining : 16.68
Demand : 16.68
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 28.43
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
4 months 1 day ago
16 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अनुबन्ध के अन्तिमिकरण की कार्यवाही की जा रही है। -- as on 28-Jun-2024
Physical Peramenters