Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.26 | 2.26 | 2.26 | 0 |
72W492 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0- ई.पत्रावली संख्या 48456 लो0नि0वि0 अनुभाग.2 देहरादून दि0 31.07.2023।
TS Amount (lakhs) : 45.11 Lacs
Financial Detail
Sanction Cost : 45.11 Lacs
Resanction Cost : 45.11 Lacs
Exp. Upto Last Fy : 28.43 Lacs
For CFY 2024-2025
Remaining : 16.68 Lacs
Demand : 16.68 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 28.43 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
2 months 2 weeks ago
05 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters