Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
72W493 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 2451/111(2)/23-01 (प्रा0आ0)/2019 दि0 21.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 550.82 Lacs
Resanction Cost : 550.82 Lacs
Exp. Upto Last Fy : 448.91 Lacs
For CFY 2024-2025
Remaining : 101.91 Lacs
Demand : 101.91 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 448.91 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। 10.00 किमी0 लम्बाई में क्रैश बैरियर का कार्य पूर्ण। शेष किमी0 में कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters