Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
72W500 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी पौडी गढवाल का पत्रांक 354/वा0जि0यो0/सा0 पत्रा0/2023-24 दि0 05.07.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 5.00 Lacs
Resanction Cost : 5.00 Lacs
Exp. Upto Last Fy : 3.38 Lacs
For CFY 2024-2025
Remaining : 1.62 Lacs
Demand : 1.62 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3.38 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
10 months 2 weeks ago
05 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित । कार्य प्रगति पर। -- as on 03-Nov-2023
Physical Peramenters