Work Profile Report [72W509]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-27910 दि0 08.09.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
139.36
Resanction Cost :
139.36
Tentative Cost :
139.36
Exp. Upto Last Fy :
41.86
For CFY 2024-2025
Remaining :
97.50
Demand :
97.50
Allotment :
50.00
Exp in CFY :
78.40
Total Up to Date Exp :
120.26
Construction Started
Sanction on : 1 year 2 months ago
08 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
60 %
Tentative Completion date on : 4 months 6 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0 1, जी0 2 एवं जी0 3 का कार्य पूर्ण। 1.00 किमी0 लम्बाई में पी0सी0 का कार्य पूर्ण। -- as on 28-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: