Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 67.9 | 67.9 | 0.000 | 67.9 | 7.450 | 7.000 |
72W518 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 5082/III(2)2023-01(प्रा0आ0)/2023 दि0 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
658.44
Resanction Cost :
658.44
Tentative Cost :
658.44
Exp. Upto Last Fy : 283.74
For CFY 2024-2025
Remaining : 374.70
Demand : 374.70
Allotment : 115.00
Exp in CFY : 164.86
Total Up to Date Exp : 448.60
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 95 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Jun-2024