Work Profile Report [72W521]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-48456 दि0 15.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
61.69
Resanction Cost :
61.69
Tentative Cost :
61.69
Exp. Upto Last Fy :
27.07
For CFY 2024-2025
Remaining :
34.62
Demand :
34.62
Allotment :
30.00
Exp in CFY :
25.89
Total Up to Date Exp :
52.96
Work completed
Sanction on : 1 year 1 week ago
15 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
95 %
Tentative Completion date on : 4 months 2 weeks ago
04 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 02-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: