Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.125 | 4.125 | 2.000 | 2.125 | 1.600 | 0.000 |
72W521 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-48456 दि0 15.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 61.69 Lacs
Resanction Cost : 61.69 Lacs
Exp. Upto Last Fy : 27.07 Lacs
For CFY 2024-2025
Remaining : 34.62 Lacs
Demand : 34.62 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 27.07 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
6 months 4 days ago
15 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters