Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.125 | 4.125 | 2.000 | 2.125 | 1.600 | 0.000 |
72W521 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 ई पत्रावली संख्या-48456 दि0 15.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
61.69
Resanction Cost :
61.69
Tentative Cost :
61.69
Exp. Upto Last Fy : 27.07
For CFY 2024-2025
Remaining : 34.62
Demand : 34.62
Allotment : 30.00
Exp in CFY : 25.89
Total Up to Date Exp : 52.96
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 90 %
Sanction on :
8 months 2 days ago
15 Nov 2023
Tentative Completion date:
1 week 6 days ago
04 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 05-Jun-2024