Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
72W523 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, उत्तराखण्ड, देहरादून का पत्रांक 1550/01 नियो0-2(एस.डी.आर.एफ.)/2023 दि0 22.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
9.40
Resanction Cost :
9.40
Tentative Cost :
9.40
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 9.40
Demand : 9.40
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
6 months 3 weeks ago
22 Dec 2023
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 30-Mar-2024
Physical Peramenters