Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 2 | 2 | 2 | 0 | ||
Span of Bridges [m] | 102 | 102 | 102 | 0 |
72W537 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ।/186367/2024 ई पत्रावली संख्या- 49198 दि0 01.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
15.79
Resanction Cost :
15.79
Tentative Cost :
15.79
Exp. Upto Last Fy : 11.15
For CFY 2024-2025
Remaining : 4.64
Demand : 4.64
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.15
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
5 months 2 weeks ago
01 Feb 2024
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। डी0पी0आर0 गठित की जा रही है। -- as on 05-Jun-2024
Physical Peramenters